Getting Ready for Weekend Deployment

Finally, we are getting ready to setup the new warehouse management system.  Beside installing the new WMS solution to the new server, we have a few data migration activities to migrate the data from the old system to the new one.

Perform data validation against system and physical inventory

  1. Open orders (merge/pull) list
  2. Open ASN (advance shipment notice) list
  3. Physical Inventory count (PI Count) as of last Friday’s operation
  4. Open/closed inventory list
  5. Receipt list
  6. Despatch list

Data Migration Activities

  • Pull Part Master and Deviation Files from system
  • Customer send Part Master and Deviation files in “SOFT COPY” to vendor
  • Validate Part Master is fully loaded and in sync with both systems
  • Send “Open Order” list to Customer for validation
  • Validate open orders list provided by Customer
  • Send “In-transit” order/inventory list to Customer for later action
  • Send PI count to Customer
  • Customer to convert inventory based upon report from existing to new system requirements (if required)
  • Advertisements

    0 Responses to “Getting Ready for Weekend Deployment”



    1. Leave a Comment

    Leave a Reply

    Fill in your details below or click an icon to log in:

    WordPress.com Logo

    You are commenting using your WordPress.com account. Log Out / Change )

    Twitter picture

    You are commenting using your Twitter account. Log Out / Change )

    Facebook photo

    You are commenting using your Facebook account. Log Out / Change )

    Google+ photo

    You are commenting using your Google+ account. Log Out / Change )

    Connecting to %s


    February 2010
    M T W T F S S
    « Jan   Apr »
    1234567
    891011121314
    15161718192021
    22232425262728

    Categories

    Enter your email address to subscribe to this blog and receive notifications of new posts by email.

    Join 443 other followers


    %d bloggers like this: